top of page

NEW CHILMARK FIRE STATION +
NEW TRI-TOWN EMS HEADQUARTERS AND AMBULANCE SERVICE
NEW CONSTRUCTION - 2021 - 2023

Chilmark Fire Station + Tri-Town EMS HQ and Ambulance Service
Keenan + Kenny Architects, Ltd.

Chilmark Fire Station + Tri-Town EMS HQ and Ambulance Service

CHILMARK FIRE STATION + TRI-TOWN EMS HEADQUARTERS AND AMBULANCE SERVICE
 

Video of proposed new Chilmark Fire Station replacing an existing building adjacent to Town Hall with a new Tri-Town EMS Ambulance service and Headquarters on the lot adjacent to Town Hall; this new EMS facility will provide services for Aquinnah, Chilmark and West Tisbury.  The adjacent lot will also include additional public parking accessed by a boardwalk between the two sites.  Finally, the existing parking lot at Town Hall will be modified and on both Town parking lots will have infrastructure installed for future electric vehicle charging stations. 

 

LOCATION: Chilmark, Martha's Vineyard, Massachusetts

 

PROJECT COST: $11,000,000  (final costs T.B.D.)

 

CONSTRUCTION START: Estimated 4th Quarter 2021

 

CONSTRUCTION COMPLETION & OCCUPANCY: Estimated 2023

ARCHITECT:  Keenan + Kenny Architects, Ltd.

CIVIL ENGINEERS:  Vineyard Land Surveying & Engineering, Inc.

STRUCTURAL ENGINEER:  Coastal Engineering Co

MECHANICAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION: Griffith & Vary, Inc.

LANDSCAPE ARCHITECT:  T.L. Studio

SPECIFICATIONS CONSULTING SERVICES:  Architx, LLC.

COST ESTIMATING SERVICES:  Rider Levett Bucknall

CODE CONSULTANT:  Jensen Hughes, Inc.

OWNER PROJECT MANAGER:  CHA Consulting, Inc.

GENERAL CONTRACTOR:  Delbrook | JKS  